Mexico–Querétaro train now employs 7,041 people in Querétaro
Good news from the Mexico–Querétaro train works: the project now employs 7,041 people directly across the four work fronts in Querétaro, according to SICT official Néstor Núñez López.
The works in the state are 40.25% complete. The four fronts (9, 10, 11 and 12) run from San Juan del Río to La Corregidora, with 545 machines and 683 cargo trucks at work.
Three stations are planned in Querétaro: San Juan del Río, El Marqués (Querétaro Central, the terminal, with an inspection and conditioning zone nearby) and La Corregidora in the capital. The full route runs just over 230 km from Buenavista in Mexico City to La Corregidora, in about two hours.
SICT will now give progress briefings every 15 days. The project also includes 56 complementary works, and 108 families in four municipalities will be relocated — about 20 relocations are already agreed.